Early works on Brisbane's new Olympic stadium at Victoria Park are running ahead of schedule. Queensland's Deputy Premier Jarrod Bleijie says 200,000 cubic metres of soil and rock have been dug out in the first 100 days, and construction of the stadium itself is due to start in mid-2027. The state has still not said what the earthworks cost.
Bleijie also confirmed that the state will pay to demolish the Gabba after the 2032 Games. "It's a state asset, so of course we're responsible," he said. No recent figure exists for knocking the ground down. Until then the government plans to spend as little as possible on it, even though an independent venues review found the Gabba falls short on disability access, roofing and lighting. If cricket makes the 2032 programme, the Gabba could still host it.
Bleijie defended the A$600 million the state will pay on delivery of the A$1.4 billion Brisbane Arena at Woolloongabba. He said the state's sale of the Gabba site would offset that sum, but he did not give an expected return.
The Games infrastructure authority, GIICA, says the National Aquatic Centre, which will replace Centenary Pool, is in the final stage of design, with about 25,000 seats planned for Games time. A report on whether the Fitzroy River in Rockhampton can host rowing and canoeing is due in the first half of 2027.
Source
Original summary by Proventier.